First, what people mean by a "Party Wall agreement"
The Act doesn't use the phrase "Party Wall agreement". It refers to Notices, consent, and a Party Wall Award. An Award is the document surveyors prepare when a neighbour dissents. When people say "agreement", they usually mean one of these.
Your neighbour consented, so there's no Award
That's fine. If Notices were properly served and your neighbour consented in writing, no surveyors or Award are needed and the works can go ahead once the notice period ends. Many owners still choose a Schedule of Condition so there's a record if damage is claimed later.
Your neighbour didn't respond
Silence isn't consent. For Party Structure (section 3) and Adjacent Excavation (section 6) Notices, if your neighbour doesn't reply within 14 days a dispute is treated as having arisen. You then send a further 10-day letter asking them to appoint a surveyor. If they still don't, a surveyor can be appointed on their behalf under section 10(4)(b), and an Award is made in the usual way.
Notices were never served
If notifiable work goes ahead without Notices, the Building Owner can't rely on the rights the Act gives them, such as the right to cut into a party wall or to access the neighbour's land. The neighbour can apply to court for an injunction to stop the works and can claim for any damage, and the usual protections of an Award don't apply.
Work has already started
Stop and get advice straight away. Where works are ongoing, Notices can often still be served for the remaining work, and surveyors appointed to deal with it. For works that are already complete, the Act can't usually be applied retrospectively, and any dispute is dealt with outside the Act. The earlier this is dealt with, the more options there are.
Selling a house without a Party Wall Award
Buyers' solicitors often ask whether Party Wall Notices were served for past works. Copies of Notices, consents or Awards help a sale go smoothly. If none exist, expect questions, and possibly a request for indemnity insurance.